Sunday I installed the last 4 sheets of T1-11 , did a lot of pick up and clean up and installed 8 duplex outlets.
Monday was a rainy and wet goof off day, but I did install another 16 feet of wiring and have 3 more single box duplex outlets installed and operational. This completes the electrical for the west and north walls. When the pups show up this weekend we can get the gable end sheathing cut and installed and the windows and door put in. During the week days I will continue with the electrical wiring. I also need to add blocking between the truss bottom chords and the shorter North and South walls to make a continuous member to help reinforce the walls for wind shear. With single top plate construction I find the gable end walls just a bit too wiggly for my liking and I feel the continuous blocking will eliminate this condition.