Oh no I am under the gun!!! lol.... we are heading out for first run on the 23rd.... so much to do yet.... I made a list of priorities... but every time I finish one item... I think of 3 more....
well first hard lesson I learned.... when I ran the wiring before I put the walls up... I only drilled a hole for the wire to come through... figuring when I put in the boxes.. that I would just cut the square out with my multi tool.... well I learned I am not that good at precision cutting with a multi tool... hopefully the face plates will cover the extra cuts.... and one of them I actually cut the wire... so had to cut higher up into the paneling so I could splice the wires back together.... so when we get back... I will need to take off that piece of paneling and either re run the wiring or put a junction box behind the wall where the splices are....
At least in the bathroom.. I could install the boxes for the TV before I put the inside piece up.... also got the Cable for the TV installed... just need to notch out the 2x2s for the path it will follow...
I just need to hook up the switches and outlets on these four boxes and they are done!!
I also got one wall up for the electrical cabinet and fit the PD4045 into place... so this weekend I can put the paneling up and secure the elect panel!!
Lots of wires to hook up!
Built the battery box... which is under the elect panel and changing seat....
I have 3 days this weekend plus a couple hours after work several of the other days... so might make it.... worse case scenario... would prob be not get the trim up... and possibly the cupboard doors....