Postby pchast » Fri Jun 23, 2023 8:44 pm

Looks good. Glad you got things dried in before the storms :thumbsup:
pchast
Platinum Donating Member
 
Posts: 2027
Images: 97
Joined: Mon Jan 28, 2013 5:47 pm
Location: Athens, NY

Re: Build 2.0 started!

Postby RJ Howell » Sat Jun 24, 2023 2:39 pm

Built out the final Pantry cab out of XPS. Working on anything over waist high being light! I ripped some of my waste FG panels and glued them in fo draw slide backing/mounting. Like what I see so far! I will fabric and paint (maybe) the outside of the cabinet and use some peel-n-stick veneer on the doors and draw fronts. Figure to back that up with some contact adhesive (water based).

Did a mockup of the wall cabinet, which will go to the ceiling, to figure out supports. Right off the back I see extending at least the bottom to the rear wall and using that open portion as a campsite shelf. Okay maybe a small rim of sorts or netting. Just liked the look as I set the mockup in place. I'll do pic or two tomorrow as it get's a little more done. ;)

I think I worked out my wall cabinet span issue and I'll get into that as I build and test. To say at least one aluminum angle and some FG panels will be used. Working out the draw slide mounting with the FG panel has me thinking! :twisted:
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am

Re: Build 2.0 started!

Postby RJ Howell » Sun Jul 09, 2023 7:12 am

Time for some pic's!
Finally got back to finishing the hatches.

Image

I did this differently this time with the seal being inside vs. on the surface. Using aluminum angle to be the frame/stop and gasket seal with Sikafles as the mounting and joints seal. Did a cove rout on the upper lip of the door to aid moving water over the face and ended up mounting some Z bar over the top to work as rain diverter.

Image Image

Works well!

Added turnbuckles this time at midship as a bracket wasn't working out and I like the different point of contact it makes. Now I have front/rear on bolted mounts Mounts welded on) and the mid turnbuckles. This makes removal easier than the F150 build!

Image
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby RJ Howell » Sun Jul 09, 2023 7:14 am

Interior has changed a bit as well!

Image

Windows still have not arrived... arg
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby RJ Howell » Sun Jul 09, 2023 8:05 am

Just finished the update for the build https://bywaysnohighways.com/?page_id=1283

Have a peek if so interested.
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby RJ Howell » Sun Jul 09, 2023 9:42 am

For those that like video.. Excuse the mess

RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby rjgimp » Wed Jul 12, 2023 1:35 pm

Fantastic!
:thumbsup:
-Rob


I hope to make it to a Procrastinators Anonymous meeting someday...
just as soon as the steering committee gets around to scheduling one!
User avatar
rjgimp
500 Club
 
Posts: 785
Images: 7
Joined: Fri Feb 22, 2019 3:59 am
Location: Saint Paul MN
Top

Re: Build 2.0 started!

Postby RJ Howell » Wed Jul 12, 2023 3:28 pm

Just got word! My windows are here on Tuesday!!! :D

Also my 180° awning is here on Friday!!! :D
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby featherliteCT1 » Wed Jul 12, 2023 7:55 pm

My fingers are crossed for your timely delivery :thumbsup:
featherliteCT1
1000 Club
1000 Club
 
Posts: 1125
Joined: Wed Dec 28, 2016 6:54 am
Location: Southern Indiana
Top

Re: Build 2.0 started!

Postby RJ Howell » Fri Jul 14, 2023 4:28 pm

With windows coming Tuesday I feel the 4th quarter press coming on!

>I need more veneer, but not here till mid August.. Oh well, some cabinets fronts are FG panel only. I can live with that :)

>Ordered the balance of my electrical needs, which are actually fairly small. I'm missing my two USB/12v charge panels and coming by Monday. Some additional wiring for who knows what.. But ready :)

>Plumbing I found I don't have on hand what I need and will get tomorrow at that Box Store I so despise.. My local Ace doesn't have what I need.. Water pickup worked, and drain work fantastic! Now the right tubing to fit it all.. :)

>Counters fitted and ready. I mean both sides! Lift top over frig ready for install and the lift table built, I need to design/make the leg. I'll get into that at some point..

>Balance of wall panels need to be cut. I'm templating and fitting, so once the windows are here most of the work is done. Or so I hope...

>Ceiling.. This is an ongoing battle.. I don't like blocking out all the light, yet don't want all that light or heat transference.. I think I have a solution and may sound deaden a bit. Ongoing process on the ceiling.. Another point I'll get to.

Hard week and a half coming, but I'm up for it! :twisted: What's life without a Challenge or two?
Plan on traveling, having a beverage or three and relaxing on a run soon! :D
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby RJ Howell » Tue Jul 18, 2023 5:03 pm

First of 5 windows installed! Arrived today and worked through everything... I'm ready for tommorow and installing the balance! Took one heck of a gamble to save $1200 and it worked! Researched and bought from a Alibaba supplier. I'll past info if you want.

Image
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby bdosborn » Tue Jul 18, 2023 9:57 pm

Have a good trip!
Bruce
2009 6.5'X11' TTT - Boxcar
All it takes is a speck of faith and a few kilowatts of sweat and grace.
Image
Boxcar Build
aVANger Build
User avatar
bdosborn
Donating Member
 
Posts: 5494
Images: 772
Joined: Wed May 05, 2004 11:10 pm
Location: CO, Littleton
Top

Re: Build 2.0 started!

Postby RJ Howell » Thu Jul 20, 2023 6:53 am

Image Image

Oh ya I'm stoked! Finishing the interior oner the next couple days. Getting real close now!!
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby RJ Howell » Thu Jul 20, 2023 3:36 pm

Just saw the latest report of iceberg sights! 8 more!! I've never and hoped for seeing on this upcoming trip. I've routed this trip for several reasons. Current ETD is Wednesday the 26th. No I will not be 100%, but are we ever? As I am saying to Wifey... :D

Icebergs, Puffins and the furthest north! Knock two off the list, furthest north I hope to beat in the future. :twisted:

Okay, I need to get back to work here..
RJ Howell
1000 Club
1000 Club
 
Posts: 1163
Images: 36
Joined: Sat Jul 27, 2019 6:08 am
Top

Re: Build 2.0 started!

Postby tony.latham » Thu Jul 20, 2023 7:38 pm

You're going to have to edit the title of this thread.

Great work. And when you get a chance, the window link would be greatly appreciated.

Tony
User avatar
tony.latham
Gold Donating Member
 
Posts: 6900
Images: 17
Joined: Mon Jul 08, 2013 4:03 pm
Location: Middle of Idaho on the edge of nowhere
Top

PreviousNext

Return to General Discussion

Who is online

Users browsing this forum: No registered users and 15 guests