Correct sequence of the build

Received some bad news about the doorframes I had ordered 11 weeks ago. Instead of delivery I was informed delivery is delayed by a minimum of 8 weeks. I have tried to find an alternative, but given the bespoke dimensions there is no other option than to sit it out.
I am almost finished with the roof, wiring it up, putting in the insulation and closing up the roof leaves the hatch and the skinning on my to do list.
I think it is necessary to skin the roof of the trailer before the build of the hatch can begin, or is that not correct?
And what is skinned first? The roof or the walls?
Input will be much appreciated.
Menno
Verzonden vanaf mijn iPhone met Tapatalk
I am almost finished with the roof, wiring it up, putting in the insulation and closing up the roof leaves the hatch and the skinning on my to do list.
I think it is necessary to skin the roof of the trailer before the build of the hatch can begin, or is that not correct?
And what is skinned first? The roof or the walls?
Input will be much appreciated.
Menno
Verzonden vanaf mijn iPhone met Tapatalk